Substation Relay Protection Analyze After Interconnection of Enterprise-owned Power Plant |
Chen Shaowei1, Li Zhilei2 |
1. Beijing Chaoyang Power Supply Company, Beijing 100102; 2. Handan Power Supply Company of Hebei Province, Handan Hebei, 056035 |
|
|
Abstract Protection arrangement, action analysis and setting are considered to analyze the impact to substation when enterprise-owned power plant merge network, a protection arrangement scheme when enterprise-owned power plant merge 110kV network are proposed to decrease the influence to main system equipment.
|
Published: 10 October 2013
|
|
|
|
Cite this article: |
Chen Shaowei,Li Zhilei. Substation Relay Protection Analyze After Interconnection of Enterprise-owned Power Plant[J]. Electrical Engineering, 2013, 14(10): 41-43.
|
|
|
|
URL: |
http://dqjs.cesmedia.cn/EN/Y2013/V14/I10/41
|
[1] D1255—2001 电力系统安全稳定导则[S]. [2] 崔家佩, 等. 电力系统继电保护与安全自动装置整定计算[M]. 北京: 中国电力出版社, 1993. [3] 王维俭. 电气主设备继电保护原理与应用[M]. 北京:电力出版社, 1996. [4] 电力系统继电保护实用技术问答[M]. 北京: 电力出版社, 2000. [5] 变电运行技术问答高压设备部分上册[M]. 北京: 水利电力出版社, 1976. |
|
|
|