Combined peak shaving method of pumped storage power hydro-power and thermal power based on multi-objective fuzzy optimization |
Wang Jingjing1, Wu Xu1, Wang Zhengfeng1, Wang Naijing2, Zhang Dabo2 |
1. State Grid Anhui Electric Power Co., Ltd, Hefei 230000; 2. School of Electrical and Automation, Hefei University of Technology, Hefei 230000 |
|
|
Abstract In order to solve the problem of peaking difficulty caused by the increasing daily load peak-to-valley difference, it is necessary to optimize the peaking output of pumped storage units, hydro-power units and thermal power units. This paper proposes the first peaking optimization model of pumped storage and hydro-power with the smallest remaining load variance and the largest hydro-power generation. The second peaking optimization model of thermal power plant is constructed with power generation cost and output volatility. At the same time, constraints such as unit climbing, water storage, and power generation reference flow are considered. The multi-objective problem is processed by fuzzy optimization algorithm. Finally, the rationality of the proposed model is verified by simulation.
|
Received: 04 April 2019
Published: 19 November 2019
|
|
|
|
Cite this article: |
Wang Jingjing,Wu Xu,Wang Zhengfeng等. Combined peak shaving method of pumped storage power hydro-power and thermal power based on multi-objective fuzzy optimization[J]. Electrical Engineering, 2019, 20(11): 33-38.
|
|
|
|
URL: |
http://dqjs.cesmedia.cn/EN/Y2019/V20/I11/33
|
[1] 姜延灿, 邓彤天, 张颖, 等. 600MW火电机组低负荷调峰的经济运行方式分析[J]. 汽轮机技术, 2015, 57(1): 61-64. [2] 顾煜炯, 徐婧, 李倩倩, 等. 燃煤发电机组调峰能力模糊综合评估方法[J]. 热力发电, 2017, 46(2): 15-21. [3] 张宏伟, 赵军. 抽水蓄能-火电调峰优化对污染物处理成本影响分析[J]. 中国电力, 2017, 50(3): 186-192. [4] 唐新华, 周建军. 梯级水电群联合调峰调能研究[J]. 水力发电学报, 2013, 32(4): 260-266. [5] 葛晓琳, 张粒子. 考虑调峰约束的风水火随机机组组合问题[J]. 电工技术学报, 2014, 29(10): 222-230. [6] 卢锟明, 赵文发, 黄晓华. 综合利用抽水蓄能电站初步探讨[J]. 水电与抽水蓄能, 2017, 3(6): 58-62. [7] 张津玮, 顾秀芳. 基于Gurobi的抽水蓄能电站优化运行分析[J]. 电气技术, 2018, 19(2): 22-26. [8] 丁伟, 袁家海, 胡兆光. 基于用户价格响应和满意度的峰谷分时电价决策模型[J]. 电力系统自动化, 2005, 29(20): 10-14. [9] 周建中, 吴巍, 卢鹏, 等. 响应电网负荷需求的梯级水电站短期调峰调度[J]. 水力发电学报, 2016, 35(6): 1-10. [10] 潘欢, 陈锦麟, 张党强, 等. 计及抽蓄电站调峰运行的水火电优化调度[J]. 电力科学与工程, 2013, 29(10): 1-5. [11] 周艺环, 刘正, 吴子豪. 水火电力系统短期节能发电优化调度的研究[J]. 电气技术, 2017, 18(9): 66-71. [12] Basu M.An interactive fuzzy satisfying method based on evolutionary programming technique for multiobje- ctive short-term hydrothermal scheduling[J]. Electric Power Components and Systems, 2004, 32(12): 1287-1299. [13] 陆文玲, 吴杰康. 水火电力系统短期优化调度的多目标决策评价方法[J]. 中国电机工程学报, 2011, 31(S1): 23-29. [14] 苏鹏, 刘天琪, 赵国波, 等. 基于改进粒子群算法的节能调度下多目标负荷最优分配[J]. 电网技术, 2009, 33(5): 48-53. [15] 李会安, 尚彩霞, 黄强. 多目标模糊优化理论及其在水电系统中的应用[J]. 系统工程, 2000, 18(1): 60-63, 33. [16] 李树山, 李崇浩, 唐红兵, 等. 多振动区水电站短期调峰负荷分配方法[J]. 南方电网技术, 2015, 9(8): 77-82. [17] 张勤, 张健美, 马强, 等. 求解多目标最优潮流的改进粒子群优化算法[J]. 电气技术, 2017, 18(10): 57-60. [18] 董萍, 徐良德, 刘明波, 等. 大电网多站点无功补偿协调控制的多目标混合优化方法[J]. 电工技术学报, 2017, 32(2): 271-280. [19] 周春明, 江辉, 何禹清, 等. 可中断负荷参与阻塞管理的多目标模糊优化[J]. 电网技术, 2008, 32(9): 27-32. [20] 滕长君, 李少远. 带有模糊数的多优先级多目标优化[J]. 上海交通大学学报, 2004, 38(9): 1577-1580, 1586. |
|
|
|