The Process and Implement of 500kV Transmission Line Suspensionin Sulator String Charged Water Flush |
Niu Huiwen,Zhang Haifeng,Wu Baogui,Fang Kangjian |
1. State Grid Zhejiang Electric Power Corporation Training Centre, Hangzhou 311600; 2. Shanxi Jinyuan Power Electronic Chemical Cntre Co., Ltd, Taiyuan 030000 |
|
|
Abstract Po11ution flashover of insulators is one of the key factors which causes trip fault of electrified line, charged water washing can solve the po11ution flashover of insulators effectively.The 220kV transmission line has already concluded a set of method of effective water washing.However, the 500kV transmission line charged water flush is a blank.This paper instructs the specific process and the operation practice of the 500kV transmission line suspensionin sulator string charged water flush, which can provide a reference for the launch of the 500kV charged water transmission line flush in future.
|
Published: 19 May 2015
|
|
|
|
Cite this article: |
Niu Huiwen,Zhang Haifeng,Wu Baogui等. The Process and Implement of 500kV Transmission Line Suspensionin Sulator String Charged Water Flush[J]. Electrical Engineering, 2015, 16(05): 121-123.
|
|
|
|
URL: |
http://dqjs.cesmedia.cn/EN/Y2015/V16/I05/121
|
[1] 国家电网公司组编. 带电作业操作方法 第1分册 输电线路. 北京: 中国电力出版社, 2009. [2] 易辉. 带电作业技术标准体系及标准解读. 北京: 中国电力出版社, 2009. [3] 胡毅. 带电作业工具及安全工具试验方法. 北京: 中国电力出版社, 2003. [4] GB/T 13395—2008电力设备带电水冲洗导则. 北京:中国标准出版社, 2008. |
|
|
|