Datang Lubei Power Analysis on Zero Sequence Protection Misoperation and Secondary Wiring Analysis in Plant Auxiliary Power System with 6kV Voltage Level |
Wang Maosong, Ge Zhaozhong, Li Zhanwang |
Datang Lubei Power Plant, Binzhou, Shandong 251909 |
|
|
Abstract This paper analyses zero sequence protection misoperation of Datang Lubei power plant and offers some anti-interference measures. Meanwhile, in order to avoid misoperation or refusing to move of the relay protection device, it analyses the zero sequence current transformer series-parallel of the secondary connection, when the motors are supplied with more than two cables through more than two above zero sequence current transformer.
|
Published: 10 October 2013
|
|
|
|
Cite this article: |
Wang Maosong,Ge Zhaozhong,Li Zhanwang. Datang Lubei Power Analysis on Zero Sequence Protection Misoperation and Secondary Wiring Analysis in Plant Auxiliary Power System with 6kV Voltage Level[J]. Electrical Engineering, 2013, 14(08): 34-36.
|
|
|
|
URL: |
http://dqjs.cesmedia.cn/EN/Y2013/V14/I08/34
|
[1] 中华人民共和国国家标准. GB/T 20840.8—2007. 互感器第8部分: 电子式电流互感器. [2] 国家电网公司企业标准. Q/GDW 446—2010. 电流互感器状态评价原则. [3] 袁季修. 电流互感器和电压互感器[M]. 北京: 中国电力出版社,2011. |
|
|
|