Research and application of start stop technology of no start/standby power supply for large unit connected thermal power unit |
Guo Jianxian, Jiang Zhicheng, Guo Hang |
Shenhua Funeng Power Generation Co., Ltd, Shishi, Fujian 362700 |
|
|
Abstract Two 1050MW units in a thermal power plant are connected by generator transformer unit. There is no circuit breaker at the outlet of the generator. The connection between the generator and the main transformer is full chain split phase enclosed bus. The generator is connected to 500kV power distribution device after being boosted by the main transformer. The normal unit must rely on the start-up/standby power supply provided by the start-up/standby transformer to start and stop. This project mainly studies that the generator transformer unit adopts unit connection, the thermal power unit with no circuit breaker at the generator outlet will use the main transformer reverse power transmission of adjacent units or the high-voltage station transformer of adjacent units to provide the standby power for starting when the start-up/standby power supply is not available, and the mutual standby mode will be used after the start-up of the unit to ensure the safe shutdown of the unit in case of emergency.
|
Received: 14 November 2019
|
|
|
|
Cite this article: |
Guo Jianxian,Jiang Zhicheng,Guo Hang. Research and application of start stop technology of no start/standby power supply for large unit connected thermal power unit[J]. Electrical Engineering, 2020, 21(7): 103-107.
|
|
|
|
URL: |
http://dqjs.cesmedia.cn/EN/Y2020/V21/I7/103
|
[1] 戴苏平. 发电厂电气主接线可靠性比较分析[J]. 电气技术, 2014, 15(1): 76-77, 103. [2] 俞纪维, 董纲, 宋晓斌, 等. 主变空载合闸励磁涌流的分析与探讨[J]. 电气技术, 2016, 17(5): 131-133. [3] 范振代. 10kV变电所型式特点和应用[J]. 电气技术, 2018, 19(9): 101-103. [4] DL/T5496—2015. 220kV~500kV户内变电站设计规程[S]. [5] 徐小宁. 变电站主接线方式可靠性评估与方案优选[J]. 电工技术学报, 2015, 30(12): 441-446. [6] 韩蓉, 徐千鸣, 丁红旗, 等. 模块化多电平中高压电网模拟器及其控制[J]. 电工技术学报, 2018, 33(增刊1): 165-175. [7] 潘超, 金明权, 蔡国伟, 等. 基于变压器励磁电流辨识的直流失稳与抑制策略[J]. 电工技术学报, 2018, 33(18): 4267-4276. [8] 500kV主变SFP-1215000/500现场安装使用说明书1TBEA. 710[Z]. 特变电工衡阳变压器有限公司, 2012. [9] 27kV高厂变SFF-CY-65000/27现场安装使用说明书1TBEA. 710[Z]. 特变电工衡阳变压器有限公司, 2012. [10] 福建石狮鸿山热电厂二期2×1000MW机组工程初步设计第九卷电气部分说明书[Z]. 华北电力设计院工程有限公司, 2011. [11] 1050机组继电保护定值整定计算书[Z]. 神华福能发电有限责任公司, 2019. [12] 1050MW机组集控运行规程[Z]. 神华福能发电有限责任公司, 2019. |
[1] |
. [J]. Electrical Engineering, 2016, 17(5): 131-133. |
|
|
|
|