Analysis and Control of AC and DC Series about Substation Caused by Voltage Regulation Blocking Circuits about Main Transformer |
Su Bo, Chen Gang, Yu Rong |
Zhejiang Jiaxing Electric Power Bureau, Jiaxing, Zhejiang 314000 |
|
|
Abstract Describe the anomalies and processing about "110 kV protection measurement and control device for remote communication chaos" in the process of the main transformer shock appear, Through in-depth reading of related control circuit from the main transformer on-load voltage regulating, analysis the cause of the exception occurs,Preventive measures are put forward to avoid the repeated abnormal .
|
Received: 30 July 2014
Published: 23 January 2014
|
|
|
|
Cite this article: |
Su Bo, Chen Gang, Yu Rong. Analysis and Control of AC and DC Series about Substation Caused by Voltage Regulation Blocking Circuits about Main Transformer[J]. Electrical Engineering, 2014, 15(01): 62-64.
|
|
|
|
URL: |
http://dqjs.cesmedia.cn/EN/Y2014/V15/I01/62
|