Abstract:The current transformer in the completion of the transformation or new current transformer has been Installed, there will be several circuit load test, make sure if the test of current transformer is abnormal. This paper is the analysis of current transformer with load testing, there will be found abnormal data, based on the analysis of abnormal data, detecting the equipment installation, debugging process in the presence of defects, the current two loop field acceptance step were optimized, to ensure its safe and reliable operation.
刘俊才. 优化变电站新型设备二次回路验收的步骤[J]. 电气技术, 2013, 14(12): 83-85.
Liu Juncai. Optimization the Steps of the Transformer Substation Two Loop Check before Acceptance. Electrical Engineering, 2013, 14(12): 83-85.