Distribution Substation Planning Considering Balance of Load Rate and Risk Cost |
Wang Siying1, Chang Jun2, Li Yong3, Zhao Dianping1, Li Lei1 |
1. School of Electrical Engineering, Northeast Electric Power University, Jilin, Jilin 132012; 2. State Grid Shenyang Power Supply Company, Shenyang 110000; 3. State Grid Minquan Power Supply Company, Minquan, He'nan 476800 |
|
|
Abstract Balance of load rate and risk cost are direct responses to the adaptability of substation planning results in practical applications. The mathematical model of substation planning is established, and the substation planning method considering load balancing and risk cost is put forward. Based on the risk theory, this paper establishes the cost model of equipment, substation and line, and reflects the economics and rationality of the planning result. The K-Means algorithm is used to analyze the model. The result of the case shows that the rationality of the proposed method is more reasonable than that of the traditional planning method.
|
Published: 24 October 2017
|
|
|
|
Cite this article: |
Wang Siying,Chang Jun,Li Yong等. Distribution Substation Planning Considering Balance of Load Rate and Risk Cost[J]. Electrical Engineering, 2017, 18(10): 52-56.
|
|
|
|
URL: |
http://dqjs.cesmedia.cn/EN/Y2017/V18/I10/52
|
[1] 符杨, 卫春峰, 李振坤, 等. 考虑地理信息和行政边界的变电站供区优化[J]. 电网技术, 2014, 38(1): 3728-3733. [2] 陶青松, 肖峻, 王笑一. 基于地理信息的变电站选址定容模型与算法[J]. 电力系统及其自动化学报, 2010, 22(6): 32-37. [3] 王成山, 魏海洋, 肖峻, 等. 变电站选址定容两阶段优化规划方法[J]. 电力系统自动化, 2005, 29(4): 62-66. [4] 于明, 郭华, 潘珍, 等. 基于提升供电能力的配电网协调规划探析[J]. 电气技术, 2015, 16(10): 107-110. [5] 汪臻, 盛四清, 周庆捷. 不确定环境下配电网变电站选址定容[J]. 电力建设, 2014, 35(3): 59-63. [6] 苏海锋, 张建华, 梁志瑞, 等. 基于全寿命周期成本的配电网变电站选址定容优化规划[J]. 电力系统自动化, 2012, 36(23): 59-64. [7] 苏海锋, 张建华, 梁志瑞, 等. 基于GIS空间分析与改进粒子群算法的变电站全寿命周期成本规划[J]. 中国电机工程学报, 2012, 32(16): 92-99. [8] 苏海锋, 张建华, 梁志瑞, 等. 基于改进均值聚类随机粒子群算法的变电站LCC规划[J]. 电工技术学报, 2012, 27(4): 209-215. [9] 姜小静, 苏海锋, 梁志瑞. 计及风险成本的配电网变电站规划方法[J]. 电力自动化设备, 2014, 34(6): 141-145, 167. [10] 闫丽梅, 许爱华, 任爽, 等. 一种变电站选址的新方法[J]. 高电压技术, 2007, 33(9): 75-79. [11] 何永秀, 罗涛, 方锐. 基于风险分析的变电站选址优化研究[J]. 华北电力大学学报, 2011, 38(3): 53-57, 66. [12] 张炳达, 王静. 基于熵原理的电能质量评估新方法[J]. 电力自动化设备, 2009, 29(10): 35-38. [13] 丁明, 过羿, 张晶晶, 等. 基于效用风险熵权模糊综合评判的复杂电网节点脆弱性评估[J]. 电工技术学报, 2015, 30(3): 214-223. [14] (加)李文沅, 周家启[等]译. 电力系统风险评估模型、方法和应用[M]. 北京: 科学出版社, 2006. [15] 刘秋华, 董丹丹, 韩韬. 基于层次分析法的配电网风险评估指标体系研究[J]. 电气技术, 2016, 17(9): 39-42. [16] 王璁, 李晓, 屠幼萍. 变压器质量风险的全寿命周期评估方法研究[J]. 电气技术, 2014, 15(5): 31-34, 43. [17] 周莉梅, 范明天. 城市电网用户停电损失估算及评价方法研究[J]. 中国电力, 2006, 39(7): 70-73. [18] 苑津莎, 张利伟, 李中, 等. 基于互补免疫算法的变压器故障诊断[J]. 电工技术学报, 2015, 30(24): 67-75. |
|
|
|