Analysis on overstep tripping of UHVDC converter station auxiliary power system bus-bar automatic transfer switch and its improvement |
LI Ran, SUN Yi, JIN Ming, LÜ Li |
Maintenance Branch, State Grid Jiangsu Electric Power Co., Ltd, Nanjing 211100 |
|
|
Abstract Auxiliary power system is an extremely important system in ultra high voltage direct current (UHVDC) converter station, and its reliability directly affects the safe and stable operation of converter station. The main structure of station auxiliary power system and the automatic switching- on/off logic of bus-bar automatic transfer switch (BATS) based on Huaian converter station is introduced in this paper. On the basis of that, an overstep tripping of UHVDC converter station bus-bar automatic transfer switch is analyzed and the root cause of the fault that is the design error of 10kV switch signal circuit is pointed out. For this reason, the corresponding improvement measures are put forward, and the effectiveness of the improvement is verified by experiments.
|
Received: 22 September 2020
|
|
|
|
[1] 赵畹君. 高压直流输电工程技术[M]. 北京: 中国电力出版社, 2004. [2] 许卫刚, 廖文锋, 顾舒扬. 直流输电工程站用电系统运行分析[J]. 高电压技术, 2006, 32(9): 157-159. [3] 姚其新, 饶洪林. 换流站阀水冷系统隐患分析及治理[J]. 华中电力, 2010, 23(5): 56-58. [4] 胡晓静, 李志勇, 杨慧霞, 等. 换流站站用电备自投装置设计及整定[J]. 电力系统保护与控制, 2015, 43(17): 145-148. [5] 陈晴, 周志超. ±800kV特高压换流站交流电源系统的优化设计[J]. 电力建设, 2012, 33(4): 43-45. [6] 蒙健明, 曹继丰, 王电处, 等. 兴仁换流站站用电系统备自投定值配合研究[J]. 电力建设, 2008, 29(8): 37-40. [7] 尹晓海, 王时光, 肖云亮, 等. 一例特高压站用电备自投误闭锁研究与改进[J]. 电气技术, 2018, 19(3): 130-133. [8] 汤海霞, 刘恒. 备自投装置在应用中误动作分析及解决措施[J]. 电气技术, 2012, 13(9): 80-81. [9] 程建登, 吴斌, 毛文俊, 等. 特高压换流站故障统计与反措[J]. 高压电器, 2018, 54(12): 292-298. [10] 张培鸿, 戚宏伟. 南桥换流站站用电备用电源自投的改造设计[J]. 华东电力, 2006, 34(12): 57-59. |
|
|
|