Abstract When the rotor of a turbine generator in a nuclear power plant is repaired for the first time and insulation defects occur in the winding, the rotor retaining ring should be removed by induction heating method for inspection and treatment. According to the actual situation of the power station and the demand of the retaining ring disassembly, after analysis and calculation, this paper uses the 10kV box-type substation decommissioned during the construction period as the induction heating power supply for generator rotor retaining ring according to the optimal single-winding power supply scheme, and it has been successfully applied in the first overhaul of two million-kilowatt turbogenerators and the treatment of rotor insulation defects, which effectively guarantees the overhaul period of nuclear power plant generators and saves the overhaul cost.
|
Received: 10 November 2023
|
|
|
|
Cite this article: |
SHEN Yanpeng,WANG Shengxue. Research and application of transforming 10kV box-type substation into induction heating power source for generator rotor retaining ring[J]. Electrical Engineering, 2024, 25(4): 72-76.
|
|
|
|
URL: |
http://dqjs.cesmedia.cn/EN/Y2024/V25/I4/72
|
[1] 王声学, 邹晓, 申雁鹏, 等. TBB—1000型发电机转子绕组绝缘缺陷的处理与分析[J]. 大电机技术, 2013(4): 17-20. [2] 高俊国, 孟睿潇, 胡海涛, 等. 电机定子绝缘老化寿命预测研究进展[J]. 电工技术学报, 2020, 35(14): 3065-3074. [3] 杨晓斌, 杨军. 感应加热法在发电机转子检修中的应用[J]. 黑龙江电力, 2000, 22(2): 49-52. [4] 范振代. 10kV变电所型式特点和应用[J]. 电气技术, 2018, 19(9): 101-103. [5] 王锡凡. 电力工程基础[M]. 西安: 西安交通大学出版社, 1998. [6] 李建明, 朱康. 高压电气设备试验方法[M]. 2版. 北京: 中国电力出版社, 2001. [7] 谢毓城. 电力变压器手册[M]. 北京: 机械工业出版社, 2003. [8] 电力设备预防性试验规程: DL/T 596—2021[S]. 北京: 中国电力出版社, 2021. [9] 陈天翔, 王寅仲, 温定筠, 等. 电气试验[M]. 3版. 北京: 中国电力出版社, 2016. [10] 高低压预装式变电站: GB/T 17467—2020[S]. 北京: 中国标准出版社, 2020. |
|
|
|