±800kV Converter Station NBSF Function Logic Analysis and Test Method for Improvement |
Lei Zhanfei, Shi Lei, Chai Bin, Gao Haiyang |
State Grid Ningxia Electric Power Maintenance Company, Yinchuan 750011 |
|
|
Abstract HVDC converter station control logic is much and complicated, each control logic shall be conducted in the system debugging phase detailed functional verification, the rationality of the validation method, related to the reliability of the dc system is running. In this paper, through the ±800kV LingZhou-ShaoXing DC control protection system function analysis of NBSF logic, put forward more reliable protection strategy and the control of the comprehensive test method.
|
Published: 23 May 2017
|
|
|
|
Cite this article: |
Lei Zhanfei,Shi Lei,Chai Bin等. ±800kV Converter Station NBSF Function Logic Analysis and Test Method for Improvement[J]. Electrical Engineering, 2017, 18(5): 132-135.
|
|
|
|
URL: |
http://dqjs.cesmedia.cn/EN/Y2017/V18/I5/132
|
[1] 灵州-绍兴±800kV特高压直流工程控制保护系统ACCEL软件[Z]. 2015. [2] 灵州-绍兴±800kV特高压直流工程系统联调试验故障波形图[Z]. 2015. [3] 赵畹君. 高压直流输电工程技术[M]. 北京: 中国电力出版社, 2004. [4] 灵州-绍兴±800kV直流输电工程成套设计书 [Z]. 2015. [5] 杨万开, 印永华, 曾南超, 等. 天中特高压直流输电工程系统试验方案[J]. 电网技术, 2015(2): 349-355. [6] 杨万开, 印永华, 曾南超, 等. 向家坝—上海 +800kV特高压直流输电工程系统调试技术分析[J].电网技术, 2011(7): 19-23. [7] 杨万开, 印永华, 曾南超. 锦苏特高压直流输电工程系统试验研究和实践[J]. 电网技术, 2014(1): 16-21. |
|
|
|