Analysis on an accident about power fast transfer equipment of plant power supply system misaction |
Wang Zhilong1, Huo Jing2 |
1. Power Plant of Meishan Iron&Steel Co., Nanjing 210039 2. Enery and Environment Protection Department of Meishan Iron&Steel Co., Nanjing 210039 |
|
|
Abstract Factory with fast switching of standby power supply device in power plant now has been widely used, this paper introduces a DC system of a power plant has led to a sudden power outage, plant standby power supply fast cutting device in the wrong action, resulting in a near production accident, analysis MFC2000-2 plant auxiliary power fast cutting device error action causes, and proposes targeted solutions.
|
Received: 18 July 2017
Published: 07 February 2018
|
|
|
|
Cite this article: |
Wang Zhilong,Huo Jing. Analysis on an accident about power fast transfer equipment of plant power supply system misaction[J]. Electrical Engineering, 2018, 19(2): 112-115.
|
|
|
|
URL: |
http://dqjs.cesmedia.cn/EN/Y2018/V19/I2/112
|
[1] GB/T 14285—2006 继电保护和安全自动装置技术规程[S]. [2] 陆昱, 邰能灵. 备自投合闸回路在现场运行中的改进[J]. 电力自动化设备, 2010, 30(1): 145-149. [3] 唐海东. 石化企业110kV供电系统的快切装置应用及分析[J]. 电气技术, 2015, 16(9): 102-105, 122. [4] 董德, 魏林邦, 江雨, 等. 水力发电厂直流系统故障分析与处理[J]. 电气技术, 2017, 18(6): 68-72. [5] 韩宪良. 110V直流控制系统异常时安稳误动事故分析[J]. 华电技术, 2015, 37(7): 43-44, 49. |
|
|
|