GE励磁低励限制与汽轮发电机失磁保护及进相试验配合校核
郑桂杰, 刘宁, 刘晓文, 郝宇, 孙鹏
北方联合电力有限责任公司达拉特发电厂,内蒙古 鄂尔多斯 014300
Coordination check of GE low excitation limit with field loss protection and leading phase test for turbo-generator
ZHENG Guijie, LIU Ning, LIU Xiaowen, HAO Yu, SUN Peng
Dalat Power Plant of Northerm United Power Co., Ltd, Ordos, Inner Mongolia 014300
全文: PDF (1126 KB)   HTML (1 KB) 
输出: BibTeX | EndNote (RIS)      
摘要 为防止发电机组进相运行因进相深度过大而非正常停运,提出GE发电机励磁低励限制与汽轮发电机失磁保护、进相试验配合校核方法。首先分析发电机进相运行时励磁系统低励限制与失磁保护之间的配合关系;然后根据机组实际励磁参数、发电机失磁保护定值、机组进相试验报告,校核GE EX2100励磁调节器低励限制与发电机失磁保护、进相试验间的配合是否满足要求,对不满足配合关系的低励限制参数给出调整方法。该方法简便易行,现场实例校核结果验证了其有效性。
服务
把本文推荐给朋友
加入我的书架
加入引用管理器
E-mail Alert
RSS
作者相关文章
郑桂杰
刘宁
刘晓文
郝宇
孙鹏
关键词 GE励磁低励限制失磁保护进相试验配合    
Abstract:In order to prevent the generator from abnormal shutdown due to the excessive depth of leading phase operation, this paper presents a coordination check method of low excitation limit with field loss protection and leading phase test for turbo-generator. The coordination relationship between low excitation limit and field loss protection is analyzed. Then, according to the excitation parameters, the setting value of field loss protection and the leading phase test results of the generator unit, the GE EX2100 excitation regulator is checked that its low excitation limit value matches with the generator field loss protection and leading phase test results, and the adjustment method is given for the low excitation limit parameters which do not meet the matching relationship. The method is simple and easy to implement, and its effectiveness is verified by the check results of field examples.
Key wordsGE excitation    low excitation limit    field loss protection    leading phase test    coor-dination   
收稿日期: 2021-04-06     
作者简介: 郑桂杰(1970—),女,学士,正高级工程师,从事发电厂电气二次专业技术工作。
引用本文:   
郑桂杰, 刘宁, 刘晓文, 郝宇, 孙鹏. GE励磁低励限制与汽轮发电机失磁保护及进相试验配合校核[J]. 电气技术, 2021, 22(11): 42-46. ZHENG Guijie, LIU Ning, LIU Xiaowen, HAO Yu, SUN Peng. Coordination check of GE low excitation limit with field loss protection and leading phase test for turbo-generator. Electrical Engineering, 2021, 22(11): 42-46.
链接本文:  
https://dqjs.cesmedia.cn/CN/Y2021/V22/I11/42